FH Holding Moscow Limited v AO Unicredit Bank & Anor

Neutral Citation Number: [2026] EWCA Civ 468
Case No:
IN THE COURT OF APPEAL (CIVIL DIVISION)
ON APPEAL FROM THE HIGH COURT OF JUSTICE
BUSINESS AND PROPERTY COURTS OF ENGLAND AND WALES
KING’S BENCH DIVISION
COMMERCIAL COURT
Mr Justice Henshaw
[2025] EWHC 3111 (Comm)
Royal Courts of Justice
Strand, London, WC2A 2LL
Date: 17/04/2026
Before:
LORD JUSTICE MALES
and
- - - - - - - - - - - - - - - - - - - - -
Between:
|
FH HOLDING MOSCOW LIMITED (a company incorporated in the Republic of Cyprus) |
Appellant/ Claimant |
|
|
- and - |
||
|
1)
AO UNICREDIT BANK (a company incorporated in the Russian Federation)
2)
UNICREDIT S.p.A. (a company incorporated in the Italian Republic) |
Respondents/Defendants |
- - - - - - - - - - - - - - - - - - - - -
- - - - - - - - - - - - - - - - - - - - -
Rupert D’Cruz KC and Emile Simpson (instructed by Branch Austin McCormick LLP) for the Appellant
Louise Hutton KC (instructed by Allen Overy Shearman Sterling LLP) for the Respondents
Hearing dates: 30 & 31 March 2026
- - - - - - - - - - - - - - - - - - - - -
Approved Judgment
This judgment was handed down remotely at 10.30am on 17 April 2026 by circulation to the parties or their representatives by e-mail and by release to the National Archives.
.............................
LORD JUSTICE MALES:
The principal issue in this appeal is whether proceedings in Moscow to levy execution against property mortgaged under a Mortgage Agreement, which was subject to Russian law and jurisdiction, were brought in breach of the arbitration clause in a separate Facility Agreement, which was governed by English law and provided for arbitration in Vienna. The appellant’s case is that before levying execution, the respondent banks were obliged to obtain an award from an arbitral tribunal in Vienna declaring that an Event of Default had occurred and that their failure to do so was a breach of the arbitration clause in the Facility Agreement.
It is not easy to see why this issue has anything to do with English law or the English court. Neither the Russian bank which is the claimant in the Moscow proceedings, nor the Cypriot company which is the defendant there, has any presence or conducts any business in this jurisdiction. The proceedings in Moscow are brought pursuant to a Russian law Mortgage Agreement which sets out the circumstances in which the lender is entitled to levy execution and provides that this may only be done in a judicial procedure in the Moscow court. The property in question is in Russia.
Whether the bank is entitled to levy execution without first obtaining an award in Vienna appears to me to be an issue for the Moscow court to determine, just as it would determine any other defence to the process of execution. It is an issue which depends upon interpreting what the Mortgage Agreement has to say about the circumstances in which the security may be enforced and about the jurisdiction of the Moscow court, both of which are matters of Russian law.
Moreover, the proceedings here are brought to enforce an arbitration agreement which is governed by Austrian and not English law. So (in contrast with the position in UniCredit Bank GmbH v RusChemAlliance LLC [2024] UKSC 30, [2025] AC 1177, where the arbitration clause was governed by English law) any interest of the English court in enforcing the Austrian law arbitration clause can only be derived from the fact that the underlying Facility Agreement, but not the arbitration clause with which the proceedings are concerned, is governed by English law. But that seems a shaky foundation for the grant of a remedy as serious as an anti-suit injunction.
However, the parties argued the issue before Mr Justice Henshaw, and in this court, as one to be determined applying English law principles of contract interpretation, perhaps on the basis that the applicable Russian and Austrian principles could be deemed to be the same as the equivalent English law principles. On that basis the judge concluded that the bringing of proceedings in Moscow was not a breach of the arbitration clause in the Facility Agreement. I agree with that conclusion, which means that the appeal must be dismissed. As a result it will not be necessary to decide the other issues discussed in submissions.
The parties
The appellant claimant is FH Holding Moscow Ltd (‘FHM’), a Cypriot company which operates solely in Russia, where it is tax resident. It is part of a group of companies, the ‘Fashion House’ group, which also operates in Poland, Romania, Belgium, and Luxembourg. It has no business in, or connection with, England and Wales.
The defendants and respondents are AO UniCredit Bank and UniCredit SpA (‘AO’ and ‘SPA’, together ‘the banks’). AO is a Russian bank which is a wholly owned subsidiary of SPA, a major Italian bank. SPA has, but AO does not have, a branch office in London.
The Facility Agreement
FHM is the borrower under a term loan dated 2nd November 2018 (the ‘Facility Agreement’). The loan comprised:
a Euro facility consisting of (a) €4,300,000 lent by AO and (b) €21,600,000 lent by SPA; and
a Russian rouble loan facility of RUB 1,260,000,000 lent by AO.
SPA entered into the Facility Agreement as lender. AO entered into it as lender, but also as the Security Agent. As Security Agent, AO was the party to which FHM was required to make repayments as and when they fell due and was the only party entitled to enforce the lenders’ rights under the agreement (clause 27).
Clause 23 of the Facility Agreement lists numerous events or circumstances which constitute an Event of Default. One such event, as would be expected, is a failure by FHM to pay any amount which is payable on the due date and at the place and in the currency in which it is expressed to be payable, with only limited exceptions. One of the consequences of an Event of Default is that the Agent may accelerate all or part of the loans so that they become immediately due and payable.
The Facility Agreement is governed by English law and contains an arbitration clause in the following terms:
‘42. ARBITRATION
Arbitration
Any dispute arising out of or in connection with this Agreement (including a dispute relating to the existence, validity or termination of this Agreement or any non-contractual obligation arising out of or in connection with this Agreement) (a “Dispute”) shall be referred to and finally resolved by arbitration under the Rules of Arbitration (Vienna Rules) of the Vienna International Arbitral Centre (VIAC) of the Austrian Federal Economic Chamber (the “Rules”).
Formation of arbitral tribunal, seat and language of arbitration
The arbitral tribunal shall consist of three arbitrators. The claimant(s), irrespective of number, shall nominate jointly one arbitrator; the respondent(s), irrespective of number, shall nominate jointly the second arbitrator, and a third arbitrator (who shall act as Chairman) shall be appointed by the arbitrators nominated by the claimant(s) and respondent(s) or, in the absence of agreement on the third arbitrator within 30 days of the appointment of the second arbitrator, by the Board of the VIAC (as defined in the Rules).
The seat of arbitration shall be Vienna, Austria.
The language of the arbitration shall be English.’
The effect of section 6A of the Arbitration Act 1996, inserted into the 1996 Act by the Arbitration Act 2025, is that this arbitration clause is governed by Austrian law, the law of the seat. Section 6A reverses the decision of the Supreme Court in Enka Insaat ve Sanayi AS v OOO Insurance Company Chubb [2020] UKSC 38, [2020] 1 WLR 417, which was applied and clarified in UniCredit v RusChemAlliance, according to which the default rule was that the law applicable to an arbitration agreement was the governing law of the underlying contract.
The Mortgage Agreement
The Facility Agreement was entered into alongside a suite of associated agreements, which included a Mortgage Agreement executed on 6th November 2018 between FHM as mortgagor and AO as mortgagee. SPA was not a party. Various real estate assets in or near Moscow, all of which are fashion retail outlets owned by FHM, were provided as security for the loans provided under the Facility Agreement. The total value of the assets as at 31st December 2024 is said to have been about €42 million.
The purpose of the Mortgage Agreement was to provide security for the repayment of the amounts due under the Facility Agreement. It adopted the definitions used in the Facility Agreement, including the definition of an Event of Default, which was defined in the Mortgage Agreement as ‘any event or circumstance specified as such in Clause 23 (Events of Default)’ of the Facility Agreement.
Clause 9 of the Mortgage Agreement provided as follows:
‘Clause 9.1: Right to Enforce
9.1.1: Subject to any other provisions of this Agreement and/or the Facility Agreement, the Parties agree that the occurrence of any Event of Default shall constitute a material breach of the Secured Obligations giving rise to the Mortgagee’s entitlement to levy execution of the Mortgaged Property.
9.1.2: The Parties agree that the restrictions under part 3 of Article 348 of the Civil Code and part 5 of Article 54.1 of the Mortgage Law shall not apply, and the Mortgagee may levy execution on the Mortgaged Property immediately after the occurrence of the Event of Default in accordance with the terms and conditions of this Agreement and subject to Clause 21 (Dispute Resolution).
9.1.3: The Mortgagee may levy execution under this Agreement only in a judicial procedure.
The Parties agree that the provisions of this Clause 9 represent a condition for judicial enforcement for the purposes of Chapter IX of the Mortgage Law, as follows: the Mortgagee may levy execution on the Mortgaged Property under this Agreement in a judicial procedure, in which case execution will be levied by sale of the Mortgaged Property at a public auction as a single lot (provided that the starting sale price of the Mortgaged Property at such public auction shall be equal to the Starting Price).
9.1.5: The Mortgagee shall not be obliged before exercising its right to levy execution on the Mortgaged Property in a judicial procedure to:
take any action or obtain a decision of any court, arbitration court or state authority against the Mortgagor;
file any claim or produce evidence that it has rights of claim in liquidation or insolvency proceedings against the Mortgagor; or
levy or attempt to levy execution on any other Security received in respect of the Secured Obligations. …’
The Mortgage Agreement was governed by Russian law and contained the following jurisdiction clause:
‘21.1 Any dispute arising out of or in connection with this Agreement (including a dispute regarding the entry into, validity, interpretation, breach or termination of this Agreement or the consequences of its nullity) (the Dispute), shall be referred to and finally settled by the Commercial Court of Moscow (the Court) in accordance with the laws of the Russian Federation.
For the purposes of Article 4 of the Arbitration Procedure Code of the Russian Federation, if any Dispute arises, a Party shall, before recourse to the Court, send its written claim to the other Party specifying its demands, the circumstances on which such demands are based, and any other information required to settle such a Dispute.
A claim shall be sent as provided by and to the address set out in, Clause 13 (Notices).
If there is no response to the claim or the Parties cannot resolve their Dispute within 15 (fifteen) calendar days after the day when the claim is deemed received in accordance with Clause 13 (Notices), the claiming Party may refer the dispute to the Court in accordance with Clause 21.1.’
The facts
FHM’s position is that there has never been an Event of Default under the Facility Agreement, and that it has at all material times acted in good faith to discharge its payment obligations under the Facility Agreement. In summary, it says that it made payments in full until the start of the war in Ukraine in 2022, and continued to do so until Russian counter-sanctions made it unlawful under Russian law for it to pay the Euro debt to SPA. However, it continued to service the Euro debt to AO by paying the equivalent in roubles, and that tranche was fully repaid in December 2023. It says that the rouble debt was re-scheduled in June 2023, and again in July 2024 as a result of an exchange of emails, and that it continued to make rouble payments until February 2025 when AO, at SPA’s direction, refused to accept them. This is disputed by the banks.
The Moscow proceedings
On 24th March 2025 AO (but not SPA) filed a claim in the Arbitrazh Court of the Moscow Region seeking foreclosure of the secured assets. It is common ground that that is a ‘judicial procedure’ of the kind contemplated by clauses 9.1.3 and 9.1.5 of the Mortgage Agreement. The claim was that FHM had failed to make a payment, so that an Event of Default under the Facility Agreement had occurred, entitling AO to enforce its security. The debt which it seeks to enforce is the total of the outstanding loan facilities, namely about €18.4m of principal and €3.85m of interest, and about RUB 845 million of principal and RUB 56 million of interest.
FHM’s response put this in dispute and contended that the issue whether there had been an Event of Default was subject to VIAC arbitration. On 28th April 2025 it filed an application challenging the jurisdiction of the Moscow court. Neither party has started any arbitration.
Subsequently, FHM joined SPA to the Moscow proceedings as a third party, pursuant to an application made on 28th May 2025. In Russian procedure, a ‘third party’ is a person whose interests might be affected by the court judgment, but who is not a claimant or a respondent. Although joined as a party by FHM in this way, SPA itself has made no claim in the Moscow proceedings.
FHM’s case is that in commencing the Moscow proceedings AO was acting in accordance with directions given by its parent company, SPA, and that this amounts to a breach of the arbitration clause in the Facility Agreement by SPA as well as by AO.
The English proceedings
On 7th August 2025 FHM issued its application for an anti-suit injunction against both banks. Following a without notice hearing on 11th August 2025, His Honour Judge Pelling KC granted permission to serve the application out of the jurisdiction on AO on three grounds:
pursuant to CPR PD 6B, para. 3.1(3), on the basis that AO is a necessary and proper party to the anti-suit injunction claim against SPA, over which the court has jurisdiction because SPA has a branch in London;
pursuant to CPR PD 6B, para. 3.1(6)(c), on the basis that the injunction claim is made in respect of a contract (the Facility Agreement) governed by English law; and
pursuant to CPR PD6B, para. 3.1(6)(c), on the basis that the injunction claim is made in respect of a contract (the arbitration clause in the Facility Agreement) governed by English law. (It is now accepted that jurisdiction over AO cannot be founded on this basis as the arbitration clause is governed by Austrian law).
The application came before Mr Justice Henshaw on 13th November 2025, together with a challenge by AO to the jurisdiction of the English court and an application by SPA for summary judgment. The judge was able to circulate his impressive judgment to the parties in draft only eight days later. He summarised his conclusions as follows:
‘i) I am not persuaded that there is a high probability or a high degree of assurance that the Moscow proceedings are in breach of the Arbitration Agreement.
it would be inappropriate for an ASI to be granted on the basis of the Moscow proceedings being vexatious and oppressive;
SPA’s summary judgment should be granted, on the basis that the claim against it has no realistic prospect of success; and
the English court lacks jurisdiction over AO, whose jurisdiction challenge must succeed.’
As a result the judge set aside the permission for service out of the jurisdiction on AO and dismissed the claim against SPA.
The appeal
FHM appeals on four grounds:
the judge was wrong to hold that the Moscow proceedings were not in breach of the arbitration agreement in the Facility Agreement; in particular, he was in error in his interpretation of clause 9 of the Mortgage Agreement;
the judge was wrong to hold that the English court did not have jurisdiction over AO; the claim for an anti-suit injunction was ‘in respect of’ a contract governed by English law, namely the Facility Agreement;
the judge was wrong to hold that the English court did not have jurisdiction over AO as a ‘necessary or proper party’ to the claim against SPA;
the judge was wrong to hold that it was not just and convenient to grant an anti-suit injunction against the banks, that conclusion being contrary to the established principle that such an injunction will be granted where foreign proceedings are brought in breach of contract and the court has jurisdiction, unless there are strong reasons not to do so (Renaissance Securities (Cyprus) Ltd v ILLC Chlodwig Enterprises [2025] EWCA Civ 369, [2025] 1 Lloyd’s Rep 518).
FHM has not pursued the argument which it made in the court below that, independent of any breach of the arbitration clause, an anti-suit injunction should be granted on the basis that the Moscow proceedings are vexatious and oppressive.
The respondent’s notice
As well as defending the judge’s reasoning, AO contends that the gateways on which FHM relied in order to found jurisdiction against it are not available because CPR 62.5 is the exclusive route for service out of the jurisdiction of an arbitration claim form.
The application to adduce fresh evidence
Before the judge it was the banks’ case that the words ‘arbitration court’ in clause 9.1.5 of the Mortgage Agreement (‘any court, arbitration court or state authority’) refer to an arbitral tribunal such as a VIAC tribunal constituted under the Facility Agreement. At the hearing FHM suggested for the first time that these words referred to a Russian arbitrazh court (i.e. a state body and not a private tribunal). The judge held that it would not be fair to allow FHM to take this point when the parties’ evidence had proceeded on the basis that the words referred to an arbitral tribunal.
This has led to an application by FHM to adduce fresh evidence on appeal consisting of an expert report by Victor Prokofiev on the translation of the words ‘arbitration court’, who opines that they refer to a Russian arbitrazh court. The banks oppose this application, but submit that if this new evidence is allowed, they should be allowed to adduce their own evidence of the meaning of these words.
The Moscow judgment
This appeal was expedited with a view to a decision being given before the Moscow proceedings had reached their conclusion. In the event, however, the Moscow court gave judgment on 19th March 2026, 11 days before the hearing of the appeal. It decided that the dispute fell within the terms of clause 21 of the Mortgage Agreement, that the Mortgage Agreement did not require AO to obtain a decision as to the existence of an Event of Default from a VIAC tribunal before enforcing its security, and that an Event of Default had occurred. Nevertheless it dismissed AO’s claim because AO had not obtained permission from the Russian Central Bank or from the Government Commission for Control over Foreign Investment, permission which AO was required to obtain before foreclosing as a matter of Russian law.
The dismissal of AO’s claim in the Moscow court has removed much of the urgency of this appeal, but does not mean that it is academic. It is possible, if there is no injunction, that AO may appeal to a higher court (it has one month from the date of the judgment in which to do so) or that it may obtain the necessary permission and bring new proceedings.
Are the Moscow proceedings in breach of the arbitration clause in the Facility Agreement?
It is apparent from the grounds of appeal that the question whether the Moscow proceedings were brought in breach of the arbitration clause in the Facility Agreement is potentially decisive. If there was no breach, the claim for an anti-suit injunction must fail, regardless of whether that is viewed as a matter of jurisdiction over AO or a decision on the merits so far as SPA is concerned.
It is plain that, as a matter of language, a dispute about whether there has been an Event of Default is capable of falling within both the arbitration clause in the Facility Agreement and the jurisdiction clause in the Mortgage Agreement. These can, therefore, be regarded as competing dispute resolution clauses.
The English law principles to be applied when there are apparently competing dispute resolution clauses were summarised by Lord Justice Hamblen in BNP Paribas SA v Trattamento Rifiuti Metropolitani SpA [2019] EWCA Civ 768, [2020] 1 All ER 762, para 68 (omitting citations):
‘(1) Where the parties’ overall contractual arrangements contain two competing jurisdiction clauses, the starting point is that a jurisdiction clause in one contract was probably not intended to capture disputes more naturally seen as arising under a related contract …
A broad, purposive and commercially-minded approach is to be followed …
Where the jurisdiction clauses are part of a series of agreements they should be interpreted in the light of the transaction as a whole, taking into account the overall scheme of the agreements and reading sentences and phrases in the context of that overall scheme …
It is recognised that sensible business people are unlikely to intend that similar claims should be the subject of inconsistent jurisdiction clauses …
The starting presumption will therefore be that competing jurisdiction clauses are to be interpreted on the basis that each deals exclusively with its own subject matter and they are not overlapping, provided the language and surrounding circumstances so allow …
The language and surrounding circumstances may, however, make it clear that a dispute falls within the ambit of both clauses. In that event the result may be that either clause can apply rather than one clause to the exclusion of the other …’
These were the principles which the judge applied and there is no suggestion by FHM that he misdirected himself. Rather, FHM’s case is that he reached the wrong answer. The submissions advanced by Mr Rupert D’Cruz KC on behalf of FHM in this court were essentially the same as those he had advanced to the judge, who addressed comprehensively the issue whether the Moscow proceedings were brought in breach of the arbitration clause in the Facility Agreement. The judge said:
‘53. The Claimant contends that the Moscow proceedings are brought in breach of the Arbitration Agreement as they are predicated on and raise the Disputed Issues, which are required by the Arbitration Agreement to be resolved in a VIAC arbitration. Its submissions in support of that proposition may be summarised as follows.
Under clause 9.1.1 of the Mortgage Agreement, AO’s entitlement to levy execution on the mortgaged assets is expressly predicated on “the occurrence of any Event of Default”.
The Mortgage Agreement does not define, or identify distinctly, an “Event of Default ... giving rise to [AO’s] right to entitlement to levy execution on the Mortgage Property”, as referred to in clause 9.1.1. Rather, it adopts and incorporates the terms and definitions in the Facility Agreement. That is logical, as the Mortgage Agreement provides security to the lenders for the Claimant’s payment obligations under the Facility Agreement (i.e. the “Secured Obligations”) and, therefore, is supplemental to the Facility Agreement. It is in the Facility Agreement that the Events of Default are set out.
It is common ground that there is a dispute as to (a) whether the Claimant has failed to pay an amount due under the Facility Agreement, and (b) if there has been any default, the amount thereof (which goes to the scope of the assets which would be enforced against).
Those disputes (i.e. the Disputed Issues) fall within the Arbitration Agreement, since:-
the first of them is a dispute about whether an Event of Default within the meaning of clause 23.1 of the Facility Agreement has occurred, which itself turns on the interpretation of the payment obligations therein; and
the second is a dispute about the amount of any outstanding debt from the Claimant under the Facility Agreement.
Both disputes arise out of or in connection with the Facility Agreement within the meaning of the Arbitration Agreement, and therefore are subject to the exclusive jurisdiction of a VIAC tribunal. That tribunal must determine them before any enforcement under the Mortgage Agreement based on an Event of Default can occur.
Clause 9 does not assist the Respondents. Clause 9.1.1 makes clear that an Event of Default must have “occurred” before enforcement under Clauses 9.1.2 to 9.16 can be effected. Similarly, clause 9.1.2 indicates that the Mortgagee can levy execution only “immediately after the occurrence of the Event of Default …”.
Clause 9.1.5 too is predicated on the Mortgagee having acquired “its right to levy execution”, and hence on an Event of Default having occurred. Clause 9.1.5, the Claimant submits, “does not apply to issues that precede the coming into existence of the right to levy execution, including a dispute as to whether an Event of Default has occurred”.
On the Respondents’ approach, the Mortgage Agreement jurisdiction clause would negate the Arbitration Agreement (i.e. deprive the parties of their rights under the latter) in relation to disputes about an Event of Default, which is one of the most important areas of application of the Arbitration Agreement.
Since the Arbitration Agreement in substance provides for exclusive jurisdiction over the matters it covers, the Disputed Issues cannot also be regarded as falling within the Mortgage Agreement jurisdiction clause. Thus this is not a case of the kind contemplated by BNP Paribas § [68(6)] where a dispute falls within the ambit of both clauses.
Rather, the Disputed Issues are most naturally regarded as arising under a related contract, namely the Arbitration Agreement. Events of Default are the subject matter of the Facility Agreement and not the Mortgage Agreement:-
It is the Facility Agreement that identifies Events of Default, in considerable detail, whereas the Mortgage Agreement does no more than adopt what is set out in the Facility Agreement about Events of Default.
Events of Default are defaults that arise under the Facility Agreement, not the Mortgage Agreement. The relevant Event of Default here – clause 23.1 (Non-Payment) – relates to breaches of the payment obligations under the Facility Agreement, not the Mortgage Agreement.
The right to VIAC arbitration is a valuable right, as is evident from its importance in the present case. It is wholly unrealistic to suppose, in the absence of clear words, that the parties intended the Mortgage Agreement jurisdiction clause to take away their rights under the Arbitration Agreement.
I am unable to accept those submissions.
In my view, the dispute about whether an Event of Default has occurred falls within the scope of the Mortgage Agreement jurisdiction clause, as well as the Facility Agreement Arbitration Agreement. The fact that the Mortgage Agreement imports definitions and terms from the Facility Agreement does not undermine that point: rather, it is consistent with the view that some disputes under the Facility Agreement may also be disputes under the Mortgage Agreement. The questions of whether an Event of Default has occurred, and (if so) what amount is due to the lenders, are questions that may arise under the Mortgage Agreement as well as under the Facility Agreement. The answer to the Claimant’s exclusivity point is that the parties have legislated for the position, as I note below.
Further, it cannot be said that the dispute falls more naturally within the Facility Agreement Arbitration Agreement than the Mortgage Agreement jurisdiction clause. The Mortgage Agreement operates in a specific subset of circumstances where there is a dispute over an alleged Event of Default. Moreover, the parties have legislated for the position in clause 9 of the Mortgage Agreement.
Thus, clause 9.1.1 provides that execution can be levied, by a judicial procedure, as soon an Event of Default has in fact occurred, as distinct from after a separate arbitral process has confirmed that to be the case. Clause 9.1.2 then, emphatically, provides that execution can be levied “immediately after the occurrence of the Event of Default”, though “subject to Clause 21 (Dispute Resolution)” i.e. subject to the dispute resolution procedure in the Mortgage Agreement itself. That is, in my view, consistent with an intention that clause 9 should apply not only in cases where there is no dispute between the parties, but also where there is such a dispute, which may well include whether there has been an Event of Default or not; and makes provision for such disputes. Read as a whole, clause 9.1.2 indicates that the lenders can commence the execution procedure immediately, with any dispute about entitlement being resolved, under clause 21, by the Moscow Commercial Court in which those proceedings are commenced, rather than by a two-stage procedure requiring an arbitration followed by proceedings in the Moscow Commercial Court.
That approach is also consistent with clause 9.1.3, which provides that execution can be levied only [in] a judicial proceeding. The requirement for such judicial approval, including resolution of any dispute, provides a safeguard for the borrower just as the Arbitration Agreement in the Facility Agreement does. There is thus no real question of a valuable right being removed: but, even if there were, I consider the wording of clause 9 to be clear. At the same time, the requirement to levy execution exclusively by way of a judicial proceeding makes it less likely that parties intended that some types of dispute – e.g. about whether or not an Event of Default has occurred – must be resolved by arbitration followed by further proceedings in the Moscow court.
The same view is also bolstered by clause 9.1.5. At the hearing, the Claimant suggested for first time that the words “arbitration court” in the phrase “any court, arbitration court or state authority” in clause 9.1.5 may refer to the Russian Arbitrazh Courts (sometimes translated as ‘arbitration courts’) and do not include an arbitral tribunal under the Facility Agreement Arbitration Agreement. There was no expert evidence on this point. The parties had exchanged witness statements which proceeded on the basis that this phrase did cover an arbitral tribunal: see Trusova 1st witness statement §§ 36 and 37, concluding that in the light of clause 9.1.5 “AO UniCredit was entitled to proceed to levy execution on the Mortgaged Property without first obtaining a decision from an arbitral tribunal”; and Lim 2nd witness statement § 14-35, taking issue with that proposition as a matter of construction of the transaction documents as a whole but not on the basis that the words of clause 9.1.5 do not cover an arbitral tribunal. Those witness statements are not admissible as expert evidence of the meaning of the words used in clause 9.1.5 (cf. Vizcaya Partners Ltd v Picord [2016] UKPC 5 at [60]), but they are relevant in showing what the parties reasonably believed to be in dispute between them. It would not be fair, in my view, for the Claimant to be permitted now, at the hearing, to change tack on this point. Further, if the words “arbitration court” were confined to arbitrazh courts, then (a) they would appear to duplicate the immediately preceding reference to courts, and (b) the specific exclusion of arbitrazh courts would seem particularly odd given that the execution proceedings are themselves required by clause 21 of the Mortgage Agreement to be commenced in the Moscow Commercial Court, which is (the action heading indicates) itself an arbitrazh court.
In any event, regardless of the potential controversy referred to in the preceding paragraph, the presence of clause 9.1.5 still lends support [to] what can in any event be deduced from clauses 9.1.1 to 9.1.3, namely that the parties intended that execution proceedings could be started immediately, with any disputes being resolved as part of those proceedings rather than extraneously to them. Moreover, it is unclear on the Claimant’s approach what purpose clause 9.1.5 would really serve, and Ms Trusova’s evidence on behalf of the Respondents was that she is unaware of any relevant permission that might be needed from another Russian court.
I do not agree that this construction of the documents renders the Facility Agreement Arbitration Agreement substantially nugatory. Disputes over the facilities could very well arise outside the context of mortgage enforcement, and (for example) the lenders might, separately from their security over the Russian assets, seek an arbitration award that could be enforced against the Claimant. I also disagree with the Claimant’s suggestion that this approach is belied by the fact that the Arbitration Agreement does not itself state that it is subject to clause 9 of the Mortgage Agreement: it would not necessarily be expected to, in circumstances where the documents are (as both parties contend) to be interpreted together.
For these reasons, I am not persuaded that there is a high probability, or a high degree of assurance, that the Moscow proceedings are in breach of the Arbitration Agreement.’
I agree with this analysis and there would be nothing to be gained in this one-off case by my attempting to repeat it in my own words (cf. Neumans LLP v Andronikou [2013] EWCA Civ 916, [2013] Bus LR 1152, paras 36 and 37). I add only five short points.
First, I have reached that conclusion applying the English law principles which FHM invited us to apply. But as explained at the outset of this judgment, when the issue depends on interpreting a Russian law contract including a Russian jurisdiction clause and an arbitration agreement governed by Austrian law, it is by no means obvious that this is the appropriate approach.
Second, in view of what the Moscow court has decided (see para 30 above), in order to accept FHM’s submissions we would have to conclude, applying English law, that the Moscow court’s interpretation of the Russian law Mortgage Agreement was wrong. That would be an ambitious conclusion.
Third, on both parties’ cases, there is a degree of fragmentation which cannot be avoided. On the banks’ case, there may need to be an arbitration in Vienna as well as proceedings in Moscow to enforce its security, for example if the security is insufficient to repay the outstanding debt and the banks seek an award against FHM. But on FHM’s case there is the certainty of duplication, as an award in Vienna would be a condition precedent to enforcement of the mortgage security. This seems artificial. A dispute about whether an Event of Default has occurred is exactly the sort of dispute which would be expected to arise in enforcement proceedings. There is nothing unnatural in a conclusion that such a dispute can be decided in a Moscow court when the terms of clause 21 of the Mortgage Agreement are clearly wide enough to include such a dispute; not least as it may be important to a lender, once an Event of Default has occurred, to take prompt steps to enforce its security, perhaps including the obtaining of interim relief. By interpreting ‘the occurrence of any Event of Default’ in clause 9.1.1 of the Mortgage Agreement as meaning ‘the determination by a Vienna arbitral tribunal that there has been an Event of Default’, FHM’s submission substantially negates the lenders’ ability to take such steps.
Fourth, as the judge explained, the meaning of the words ‘arbitration court’ in clause 9.1.5 of the Mortgage Agreement is not a significant issue. If these words are to be interpreted as referring to an arbitral tribunal, they provide support for (or as he put it, they bolster) the judge’s conclusion but are not critical to it. Even if they refer to an arbitrazh court, however, they still show that the parties intended that execution proceedings could be started immediately, with any disputes being resolved as part of those proceedings rather than extraneously to them. I would therefore refuse the application to admit new evidence on appeal. The Ladd v Marshall [1954] 1 WLR 1489 criteria are not satisfied, not only because the evidence could have been obtained for use at the trial, but also because it would not have an important influence on the result of the case. In any event, it would be difficult for this court to override the judge’s view that it would not be fair to allow FHM to ‘change tack’ on this issue.
Other issues
My conclusion on ground 1 means that it is unnecessary to decide grounds 2 to 4 and I do not propose to do so.
However, it is worth pointing out the potentially wide-ranging impact of FHM’s argument on ground 2. Ground 2 is that the judge ought to have held that the English court had jurisdiction over AO because its claim for an anti-suit injunction was ‘in respect of’ the Facility Agreement, which is a contract governed by English law, even though the arbitration agreement in the Facility Agreement is governed by Austrian law and it is the arbitration agreement which the English proceedings seek to enforce.
In UniCredit v RusChemAlliance in the Court of Appeal the argument proceeded on the basis that, in equivalent circumstances, the relevant contract is the arbitration agreement and not the underlying contract of which it forms part ([2024] EWCA Civ 64, para 40). That is why the question whether the arbitration agreement was governed by English law was important. UniCredit did not argue that the claim was also ‘in respect of’ the underlying contract which was expressly governed by English law. However, when the case reached the Supreme Court, UniCredit did at least canvass the possibility that it could found jurisdiction under paragraph 3.1(6)(c) of Practice Direction 6B because the claim was ‘in respect of’ the underlying contract. The Supreme Court did not decide this issue, although it is fair to say that Lord Leggatt’s reaction to the argument was not encouraging:
‘19. UniCredit argues that the arbitration agreements are governed by English law because the choice of English law in clause 11 as the governing law applies to clause 12 (the arbitration clause) as well as all the other clauses of the contract. In the courts below this was the only argument that UniCredit advanced on the governing law issue. On this appeal UniCredit raised a suggestion in its written case that, even if the arbitration agreements in clause 12 are governed by French law, UniCredit’s claim still falls within the contract gateway because English law on any view governs the rest of the bond contracts and it can be said that UniCredit’s claim is made in respect of those contracts. If this argument were thought to have any merit, there is no reason why it could not have been made in the courts below. As it is, UniCredit gave no notice that it might seek to raise this new point until after RusChem had filed its written case for this appeal. At the hearing I did not understand counsel for UniCredit to be asking the court to allow UniCredit to rely on this new argument; but if permission to do so had been sought, I would not have thought it right to give it.’
In circumstances where anything we might say on this issue would be obiter, I do not think it would be helpful to express a view, although I note that the words ‘in respect of’ have generally been regarded as extremely wide words for the purpose of establishing a sufficient connection to the jurisdiction, and that there appears to be no reason in principle why a claim could not be ‘in respect of’ more than one contract. But if FHM’s argument is well-founded, it would mean that the contract gateway is available in a case such as the present, where the real connection with this jurisdiction is minimal.
The respondent’s notice
It is similarly unnecessary to address the respondent’s notice, but here again I think it is worth saying something about it.
Ms Louise Hutton KC contended on behalf of AO that the gateways in Practice Direction 6B on which FHM relied in order to found jurisdiction against it are not available because CPR 62.5 is the exclusive route for service out of the jurisdiction of an arbitration claim form. The argument is that CPR Part 6 does not apply because CPR 62.5 ‘makes different provision’ for the service of arbitration claim forms, within the meaning of CPR 6.1. CPR 6.1 provides that:
‘This Part applies to the service of documents, except where –
another Part, any other enactment or a practice direction makes different provision; or
the court orders otherwise.
(Other Parts, for example, Part 54 (Judicial Review) and Part 55 (Possession Claims) contain specific provisions about service.)’
A claim for an anti-suit injunction made on the basis that foreign proceedings have been brought in breach of an arbitration agreement is an ‘arbitration claim’ as defined in CPR 62.2 and must therefore be started by the issue of an arbitration claim form (CPR 62.3). So it might be expected that service of an arbitration claim form out of the jurisdiction would be governed by CPR 62.5, to the exclusion of CPR 6, because CPR 62.5 makes different provision for the service of such claim forms, containing as it does specific provisions about their service, just as Parts 54 and 55 contain specific provisions for judicial review and possession proceedings.
Ms Hutton’s argument seems to me to have considerable force, but it runs up against two decisions of the Supreme Court, AES Ust-Kamenogorsk Hydropower Plant LLP v Ust-Kamenogorsk Hydropower Plant JSC [2013] UKSC 35, [2013] 1 WLR 1889, para 51, and UniCredit v RusChemAlliance, both of which proceeded on the basis that the gateways in Practice Direction 6B can be relied on for service out of the jurisdiction of an arbitration claim form, although it does not appear that the contrary position was argued in either case. Indeed, RusChemAlliance includes an extended discussion of the test for satisfying the requirement that England and Wales is ‘the proper place in which to bring the claim’ in an arbitration case, a requirement which applies to service out under Part 6, but not under CPR 62.5. Lord Leggatt explained how that test should be applied in the context of an arbitration claim, although it might be thought that his discussion of the point also demonstrated that the ‘proper place’ test, which usually has to do with forum conveniens issues, is out of place in this context and is not really concerned with arbitration claims at all.
As can be seen from cases like RusChemAlliance and the present case, the question whether Part 6 is available to found jurisdiction for an anti-suit injunction claim when the arbitration agreement provides for a foreign seat has practical significance. CPR 62.5 would not have enabled FHM to found jurisdiction over AO (and likewise would not have enabled UniCredit to found jurisdiction in the RusChemAlliance case: see para 91 of the Supreme Court’s judgment). If Part 6 was not available, the only potential basis on which permission for service out of the jurisdiction could have been given was CPR 62.5(1)(c). This provides that:
‘Subject to paragraph 2A, the court may give permission to serve an arbitration claim form out of the jurisdiction if—
… (c) the claimant—
seeks some other remedy or requires a question to be decided by the court affecting an arbitration (whether started or not), an arbitration agreement or an arbitration award; and
the seat of the arbitration is or will be within the jurisdiction or the conditions in section 2(4) of the 1996 Act are satisfied.’
However, this paragraph does not apply where the arbitration clause in question provides for a foreign seat, as in the present case and as in RusChemAlliance.
I note that in the only case cited to us which directly confronts the argument advanced by Ms Hutton in the present case, Shipowners’ Mutual Protection and Indemnity Association (Luxembourg) v Containerships Denizcilik Nakliyat ve Ticaret AS [2015] EWHC 258 (Comm), [2015] 1 All ER (Comm) 966, para 42, Mr Justice Teare considered that ‘it would be a bold step for a first instance judge to say that an observation of the Supreme Court was in error’. Much the same might be said about the Court of Appeal. It is, however, an issue which might usefully be considered by the Rules Committee, who would be best placed to answer the policy questions whether the Part 6 gateways should be available for service of arbitration claim forms out of the jurisdiction and in what circumstances such service should be permitted in the case of arbitrations with a foreign seat.
LORD JUSTICE POPPLEWELL:
I agree.
LORD JUSTICE LEWISON:
I also agree.